Ridgeview Park Playground Replacement

  • Project typeExisting Park - Update
  • Project scheduleSeptember-November 2026
Ridgeview Park playground

Ridgeview Park is getting a new playground supported by the 2050 Tax Initiative and the Parks Infrastructure Replacement Plan in 2026. The new playground will consider the existing types of play equipment available at the nearby McGraw Elementary School while maximizing different kinds of play for different age groups, including accessible options and play structures designed for kids aged 2-12.

Construction is set to begin Sept. 28, 2026, weather conditions permitting.

Project Milestones

Playground Feedback Survey

In spring 2026, a survey was conducted to understand the community's preferences for the Ridgeview Park play area update. The survey was open from March 27-April 17. Notifications about the survey were posted on Nextdoor, in the McGraw Elementary Parent Teacher Organization's newsletter, on the project webpage and on yard signs around the playground for three weeks. 

Engagement Summary

  • Number of Survey Responses: 22

Concept Preference

  • When asked which option of play equipment was preferred for children 5-12:
    • 41% (9 people) preferred a dome-shaped rope climber with different climbing challenges inside and out.
    • 54.5% (12 people) preferred a themed play tower with climbing balancing, slides and play panels.
    • One participant had no preference.
  • When asked why they preferred their option, respondents noted:
    • Unique features
    • Variety
    • Climbing, balancing and upper body challenges 
  • When asked what age children frequent the area currently, responses varied but generally included toddlers to 12-year-olds. 
  • Overall, comments about the playground and park in general are summarized as the following:
    •  A desire for more features targeted for older children
    • A desire for shade
    • More versatility and tactile features in the play equipment
    • Would like to see a strong theme element
    • Enjoyment of other park features such as benches, bathroom, little library, large green space, trees and rocks
    • A desire for additional amenities throughout the park
    • Concern about the cost of equipment replacement

Start of Construction

Construction is planned to start on Ridgeview Park playground Sept. 28, 2026. The playground renovation will include updated play structures for children ages 2-12 years with a hiking theme. Construction is anticipated to complete in November 2026. 

If you have any questions about this project, please reach out to the Park Planning and Development team at ParkPlanning@FortCollins.gov.

 

More About the 2050 Tax Initiative

The 2050 Tax Initiative, approved by Fort Collins voters in 2023, allocates funds specifically to Parks, Recreation, Transit, and Climate. Funds invested through the Parks Division will support the replacement, upgrade, maintenance, and accessibility of park facilities.  

Location

4700 Hinsdale Drive, Fort Collins, CO 80526  View Map

Google Map